Your building needs a TM44 inspection if the air conditioning (AC) systems you control have a combined effective rated output above 12kW. An accredited energy assessor must inspect those systems at least every five years. The duty comes from the Energy Performance of Buildings (England and Wales) Regulations 2012. The assessor follows the TM44 methodology from the Chartered Institution of Building Services Engineers (CIBSE) and lodges the report on a government register.

Your building needs a TM44 inspection if the air conditioning (AC) systems you control have a combined effective rated output above 12kW. An accredited energy assessor must inspect those systems at least every five years. The duty comes from the Energy Performance of Buildings (England and Wales) Regulations 2012. The assessor follows the TM44 methodology from the Chartered Institution of Building Services Engineers (CIBSE) and lodges the report on a government register.

If you look after AC in offices, shops, or multi-let buildings, the sections below cover scope, responsibility, the report, and penalties.



Does my building need a TM44 inspection?

The 12kW threshold applies to the combined output of the AC units you control. Several small units can add up to one system in scope. The GOV.UK guide to air conditioning inspections treats all the units in a building under one person's control as a single system, even when each sits below 12kW. Systems in separate buildings are not added together, so each building is assessed on its own unless the buildings share plant.

The rules apply in England and Wales. Scotland and Northern Ireland have separate requirements, so check local guidance for sites there. Buildings where combined output can pass 12kW include:

  • Offices: split or central AC systems
  • Retail units: comfort cooling installed across the shop floor
  • Hotels: fifty rooms with a 3kW unit each add up to 150kW before reception and restaurant areas are counted
  • Multi-tenanted buildings: the landlord's central system and any system a tenant has installed are each counted by who controls them, so one building can need two reports

Cooling for server rooms and storage areas is not excluded either. GOV.UK says no exemption limits inspections to comfort cooling.

How do you work out your system's output?

Start with the rating plate on each unit, then cross-check the operation and maintenance (O&M) manual and your maintenance records. Add together the outputs of every unit you control in the building. As a rough guide, GOV.UK puts the floor area that needs 12kW of cooling at about 200 m² for a general office with typical electrical equipment, about 100 m² for an office with high IT loads, and about 250 m² for retail with average display lighting. Densely occupied rooms can pass 12kW on a smaller floor area, so check the plates rather than relying on floor area alone.



When is a TM44 inspection due?

The 2012 regulations require inspections no more than five years apart. For systems put into service on or after 1 January 2008, the first inspection is due within five years of that date. Older systems had fixed deadlines: 4 January 2009 for systems above 250kW and 4 January 2011 for systems above 12kW. Both dates have passed, so any older system in scope should already have a report.

What if you've just taken over a system?

The person handing over control must pass the latest TM44 report to you. If you take over a system and don't receive a report, you must arrange an inspection within three months of taking control.



Who is responsible for a TM44 inspection?

The person who controls the AC system holds the duty. They must make sure the inspection happens, keep the latest report, and hand it to anyone who takes over control. GOV.UK sets out who counts as being in control:

  • System owner: usually the controller, even when day-to-day operation is contracted out
  • Occupier who takes total responsibility for the building and its services: the controller, for example on a full repairing and insuring (FRI) lease
  • Facilities management (FM) or servicing company: can become the controller by contract, but the landlord or occupier keeps a parallel duty
  • Occupier who installs a system: responsible for that system

If you're a landlord with an FM contract in place, check that the contract names the controller and ask for a copy of each report.



How do you prepare for a TM44 inspection?

Clear access and complete records keep the visit on plan. Incomplete documentation can reduce the effectiveness of the assessment and raise its cost, because the assessor has to track down information on site. Have the following ready before the visit:

  • System documentation: manufacturer details, installation dates, and the rated cooling output for each unit
  • Maintenance records: service history, recent repairs, planned maintenance schedules, and F-gas refrigerant handling and leak check logs
  • Site access: keys, permits to work, and any escort requirements for plant rooms, roof areas, and risers
  • Site contact: someone available on the day who knows the building's AC layout and how each system operates

Equipment may sit on roofs, in plant rooms, or in other spots with limited access. Agree safe access arrangements with the assessor in advance.

Joblogic's asset register records each unit's make, model, serial number, location, installation date, and condition, and custom fields can hold the rated output. Service history sits against the asset, so the details an assessor asks for are in one place across every site.



What happens during a TM44 inspection?

The assessor examines your AC systems and their records, then writes a report. The inspection involves no cleaning, adjustments, or other physical work on the equipment. The assessor looks at:

  • Refrigeration and heat exchange: a brief check for damage or lack of maintenance that would cut efficiency
  • Air moving systems: fans, filters, heat exchangers, and grilles, including any blockages
  • Controls: set temperatures, operating times, control zones and sensors, and whether cooling and heating can run at the same time
  • Records: documentation and maintenance evidence, including any planned maintenance schedule

Does a servicing contract cover TM44?

A servicing contract does not replace a TM44 inspection. Routine maintenance and F-gas leak checking are separate duties, and they should happen more often than the five-yearly inspection. Understanding the cost of F-gas non-compliance shows why those records matter.



What does a TM44 report cover?

The report must cover the system's likely efficiency, any faults, and the adequacy of maintenance, controls, and settings. It also compares the system's size with its cooling load, then ends with a summary and key recommendations. The assessor places the system in one of three efficiency categories:

  • Impaired: efficiency reduced by faults, neglect, or misuse
  • Below current standards: likely to fall short of current minimum provisions because of its design or use
  • Acceptably efficient: the assessor judges the system's efficiency acceptable

Advice comes at three levels: fault rectification, improvements to meet current minimum provisions, and best practice. The best practice advice is a useful starting point if you're working on energy efficiency across your sites. Recommendations can cover areas such as:

  • Controls: adjusting time switches, temperature setpoints, or control zones
  • Maintenance: cleaning or repairing equipment whose efficiency has suffered through neglect
  • System replacement: flagging older, less efficient, or oversized systems

Do you have to act on the recommendations?

There's no legal requirement to act on TM44 recommendations. Keep the report, as it informs the next inspection, and treat the recommendations as a list of possible follow-up jobs.

How do you check a TM44 report is valid?

Reports produced on or after 6 April 2012 must be lodged on the Energy Performance of Buildings Register to be valid. Each lodged report has a unique reference number. You can search for and download lodged reports through the government's find an energy certificate service. If you can't find a report for a system in scope, treat it as missing.



What are the penalties for not having a TM44 report?

Trading Standards enforce the regulations. GOV.UK states the fine for not having an inspection as £300. If Trading Standards ask for a copy of the report and you don't provide it within seven days, a further £200 penalty can follow. They can request a report up to six months after the last day for compliance.

If you think a penalty notice was issued incorrectly, you can ask for a review. If you're still unhappy with the outcome, you can appeal to the county court within 28 days of being told the notice has been confirmed. Occupiers of a building where the owner controls the central system aren't liable for a penalty. A missing report can also affect the sale or letting of a building.

The government's consultation on reforming the regime proposed a new penalty charge of £800 for not having a report, and its further response on air conditioning inspection reports is due in 2026. Until the law changes, £300 is the figure in current GOV.UK guidance.


 

How do you manage TM44 inspections across multiple sites?

One report in a shared folder is easy to track. Ten buildings with staggered five-year cycles and open recommendations are harder, especially when records sit in inboxes and spreadsheets. Due dates slip, and remedial work goes unrecorded against the right asset. The gap between actioning a recommendation and proving you actioned it is where many compliance problems in heating, ventilation, air conditioning, and refrigeration (HVACR) start.

A Computerised Maintenance Management System (CMMS) or field service management (FSM) platform brings these records together. In Joblogic, you can:

  • Asset register: hold each AC unit's details and location against the asset, with the latest TM44 report attached to it
  • Planned maintenance: schedule routine servicing for each unit through planned maintenance scheduling
  • Follow-up jobs: raise a job for each recommendation you choose to act on and track it to completion across every site
  • Job notes and photos: let engineers capture evidence on site and attach it to the relevant asset

With compliance tracking in the same system, you can see what's due across the estate without checking each site by hand. Remedial work outside a PPM contract arrives as a reactive maintenance job. Link it to the asset and set the scope when you raise it, so the engineer arrives with the TM44 context they need.



How do you stay ahead of your next TM44 inspection?

Start with three checks for each building: who controls the AC, whether combined output passes 12kW, and whether a valid report sits on the register. Those answers show where you're exposed today.

Then record each next inspection date against the asset, alongside the recommendations you've chosen to act on. If calendar alerts and saved PDFs are doing the tracking today, you may recognise some of the signs that a business is outgrowing its systems.

To see TM44 reports and follow-up jobs held together on each asset, book a demo and our team will walk you through it.





FAQs

Does a residential property with air conditioning need a TM44 inspection?

It depends on the system's effective rated output. The regulations apply to systems above 12kW and treat every unit one person controls in a building as a single system. A residential property needs an inspection only if the units under one person's control add up to more than 12kW, so check the rating plates if you're unsure.

Who is responsible for a TM44 inspection in a leased commercial building?

The person who controls the AC system is responsible. That is usually the system owner, even when day-to-day operation is contracted out. An occupier who takes total responsibility for the building and its services, for example on a full repairing and insuring lease, controls the system, and an occupier who installs a system is responsible for it. A contracted FM company can take on control, but the landlord or occupier keeps a parallel duty.

What accreditation must a TM44 assessor hold?

The assessor must be a current member of a government-approved accreditation scheme. They must then lodge the report on the Energy Performance of Buildings Register for it to be valid. You can check an assessor through the register's search facility, or ask them for their scheme name and membership number.

Does a TM44 report transfer to a new owner or occupier?

Yes, the person handing over control must give you the latest report. Check it's lodged on the register and covers the systems in use. If you take over a system without a report, arrange an inspection within three months.

Are TM44 recommendations legally enforceable?

No, you don't have to act on TM44 recommendations. The legal duty is to have a valid inspection report. Failing to have one carries a £300 fixed penalty, plus £200 if you don't provide a copy within seven days of a Trading Standards request.

Joblogic

Head of Content & Engagement, Joblogic.

Dan Plume leads content and engagement at Joblogic, working with UK service businesses on how they grow without losing control of margin. He writes about the operational patterns behind growth: admin, compliance, scheduling, and the systems that hold a business together.

Let’s make your next working day better.

One conversation about your operation. A clearer view of what comes next.